MANSFIELD – The following construction projects are anticipated to affect highways in Richland County next week. All outlined work is weather permitting.

U.S. Route 30 major rehabilitation – U.S. 30, from State Route 309 to just east of the 5th Avenue ramps, will have single lane closures for a major rehabilitation project. Traffic will always be maintained.

CONTINUING IMPACTS

The contractor shifted the westbound traffic into the new phase. This started the contraflow traffic pattern with the use of crossovers at each end of the project, placing the westbound traffic on the median side of the eastbound lanes.

One lane will be maintained westbound from just east of 5th Avenue to SR 13, and two lanes of traffic westbound from SR 13 to just west of Trimble Road.

S. 30 westbound access to exits at 5th Avenue, SR 13, Trimble Road, and SR 309 are currently being maintained. Access from U.S. 30 westbound to SR 545 and SR 39 will not be permitted (ramps closed).

Construction of the U.S. 30 westbound lanes and reconstruction of the ramps is tentatively scheduled to be complete September 2021.

Closure of the U.S. 30 westbound exit and entrance ramps to SR 545. The detour route will be U.S. 30 westbound to the SR 13 exit, south on SR 13 to Longview Avenue, and east on Longview Avenue to SR 545.

Closure of the U.S. 30 westbound exit and entrance ramps to SR 39. The detour route will be U.S. 30 westbound to the Trimble Road exit, south on Trimble Road to U.S. 30 eastbound, and U.S. 30 eastbound to the SR 39 exit.

Closure of the 5th Avenue entrance ramp to U.S. 30 westbound. The detour route will be 5th Avenue to U.S. 30 eastbound, east on U.S. 30 to the Reed Road exit, and north on Reed Road to U.S. 30 westbound.

Traffic will be maintained in one lane of traffic eastbound from just west of SR 309 to SR 13, and two lanes of traffic eastbound from SR 13 to just east of 5th

Lane widths will be 11’ throughout the length of the project.

All eastbound exits will be maintained throughout the season, except for the SR 545 exit which has been permanently removed per project plans.

Eastbound and westbound traffic will be separated by portable concrete barrier throughout the length of the project.

Estimated completion of entire project: May 2023

State Route 61 resurfacing – State Route 61, from just south of London West Road to SR 98, will have single lane closures for a smooth-seal resurfacing project.

NEW IMPACTS

Bridge work has been completed on the structure between Bistline Road and Shoup Road.

The contractor will be starting pavement repairs at the end of next week.

Estimated completion: July 2021

State Route 96 resurfacing – State Route 96, from just west of Technology Parkway to the SR 13/SR 96 junction, will have single lane closures for a smooth-seal resurfacing project.

NEW IMPACTS

Bridge work has been completed at the following locations: structure over Bear Run, just east of Plymouth Springmill Road; the two structures between Bowman Street and Richland Run Road; and the two structures between Rome South Road and SR 13/SR 96.

The contractor will be starting pavement repairs at the end of next week.

Estimated completion: July 2021