MANSFIELD – The following construction projects are anticipated to affect highways in Richland County next week, according to the Ohio Department of Transportation.

All outlined work is weather permitting.

State Route 13 bridge repairs

State Route 13, at the bridge between Ogle Street and state Route 97, will have daytime single lane closures as needed for bridge painting. The overhead clearance will be reduced to 14’ 6”. Traffic will be maintained by traffic control signals. Estimated completion: August 2020

U.S Route 30 major rehabilitation

U.S. 30, from state Route 309 to just east of the 5th Avenue ramps, will have single lane closures for a major rehabilitation project. Traffic will always be maintained.

U.S. 30, from state Route 309 to just east of the 5th Avenue ramps, will have single lane closures for a major rehabilitation project. Traffic will always be maintained.

NEW IMPACTS

Nighttime lane closures – U.S. 30, between 5th Avenue and Trimble Road, will have nighttime, single lane closures from 6 p.m. to 7 a.m. to complete pavement repairs beginning Monday, June 1. This work is scheduled to be complete in two night shifts.

Begin construction on state Route 39 – Crews will begin working on the east side of Route 39 while maintaining traffic on the west side

Longview Avenue is tentatively scheduled to close Monday, June 8

CONTINUING IMPACTS

U.S. 30 westbound ramp to Route 39 northbound is closed permanently per project plans – detour route is posted

Earthwork continues at the state Route 39 northbound ramp to U.S. 30 eastbound and along Longview Avenue – traffic will be maintained in both of these areas as the contractor prepares for future temporary closures of the ramp and Longview Avenue

Estimated completion: May 2023

NEW IMPACTS

Begin construction on state Route 39 – Crews will begin working on the east side of Route 39 while maintaining traffic on the west side

Longview Avenue is tentatively scheduled to close Monday, June 8

CONTINUING IMPACTS

U.S. 30 westbound ramp to Route 39 northbound is closed permanently per project plans – detour route is posted

Earthwork continues at the state Route 39 northbound ramp to U.S. 30 eastbound and along Longview Avenue – traffic will be maintained in both of these areas as the contractor prepares for future temporary closures of the ramp and Longview Avenue

Estimated completion: May 2023

State Route 96 culvert replacement

NEW IMPACTS – State Route 96, just west of Laser Road, will close Monday, June 8 for a culvert replacement. The detour route for eastbound motorists will be state Route 96 to Route 61, north on Route 61 to Route 603, southeast on Route 603 to Route 13, south on Route 13 to Route 96 and reverse for westbound motorists. Estimated completion: Friday, June 19, 2020