Road Closed

MANSFIELD – The following construction projects are anticipated to affect highways in Richland County next week. All outlined work is weather permitting.

State Route 13 culvert replacement – State Route 13, just south of Baseline Road, will close Monday, July 26 for a culvert replacement. The detour route for northbound motorists is SR 13 to SR 603, northwest on SR 603 to SR 61, north on SR 61 to U.S. 224, east on U.S. 224 to SR 13, and reverse for southbound motorists. Estimated completion: Friday, July 30, 2021

U.S. Route 30 major rehabilitation – U.S. 30, from State Route 309 to just east of the 5th Avenue ramps, will have single-lane closures for a major rehabilitation project. Traffic will always be maintained.

CONTINUING IMPACTS

U.S. 30 eastbound – One lane of eastbound traffic will be maintained from just west of SR 309 to SR 13, and two lanes of traffic eastbound from SR 13 to just east of 5th Avenue.

U.S. 30 westbound – One lane of westbound traffic will be maintained from just east of 5th Avenue to SR 13, and two lanes of traffic westbound from SR 13 to just west of Trimble Road.

U.S. 30 westbound access to exits at 5th Avenue, SR 13, Trimble Road, and SR 309 are currently being maintained. Access from U.S. 30 westbound to SR 545 and SR 39 will not be permitted (ramps closed).

Construction of the U.S. 30 westbound lanes and reconstruction of the ramps is tentatively scheduled to be complete September 2021.

Closure of the U.S. 30 westbound exit and entrance ramps to SR 545.

Closure of the U.S. 30 westbound exit and entrance ramps to SR 39. The detour route will be U.S. 30 westbound to the Trimble Road exit, south on Trimble Road to U.S. 30 eastbound, and U.S. 30 eastbound to the SR 39 exit.

Closure of the 5th Avenue entrance ramp to U.S. 30 westbound. The detour route will be 5th Avenue to U.S. 30 eastbound, east on U.S. 30 to the Reed Road exit, and north on Reed Road to U.S. 30 westbound.

Lane widths will be 11’ throughout the length of the project.

All eastbound exits will be maintained throughout the season, except for the SR 545 exit which has been permanently removed per project plans.

Eastbound and westbound traffic will be separated by portable concrete barrier throughout the length of the project.

Estimated completion of entire project: May 2023

U.S. Route 30 bridge repair – U.S. 30 westbound, under Reed Road, will have the driving lane closed for a bridge repair project. Crews will be repairing the structure on Reed Road over U.S. 30. Estimated completion: July 2021

U.S. Route 30 interchange improvements – U.S. 30 eastbound, at the entrance ramp to I-71 northbound, will have single lane closures for interchange improvements. Crews will be constructing a full-length eastbound deceleration lane at the entrance ramp.

CONTINUING IMPACTS

The U.S. 30 eastbound to I-71 northbound entrance ramp is closed for construction of the deceleration lane extension from U.S. 30 eastbound to I-71 northbound. The detour route from U.S. 30 eastbound to I-71 northbound will be to continue on U.S. 30 to the Koogle Road ramp to I-71 northbound. Estimated reopening of entrance ramp: September 2021

The I-71 northbound exit ramp to U.S. 30 westbound is closed for construction of the deceleration lane extension on U.S. 30 eastbound. The detour route for motorists coming off of I-71 northbound to U.S. 30 westbound will exit off of I-71 and continue onto U.S. 30 eastbound to the Koogle Road exit and re-enter on the U.S. 30 westbound. Estimated reopening of exit ramp: September 2021

Estimated completion: September 2021

U.S. Route 42 resurfacing – U.S. 42, from Park Avenue East to Indiana Avenue, will have single lane closures for a resurfacing project. Crews will be performing catch basin reconstruction work along various locations within the project limits. Traffic will be maintained by flaggers. Estimated completion: September 2021

State Route 61 resurfacing - State Route 61, from just south of London West Road to SR 98, will have single lane closures for a smooth-seal resurfacing project. Traffic will be maintained by flaggers. Estimated completion: July 2021

State Route 61 culvert replacement – State Route 61, between Brannon Road and Settlement East Road, is closed for a culvert replacement. The detour route for southbound motorists will be SR 61 to SR 314, south on SR 314 to W. Fourth Street, west on W. Fourth Street to U.S. 30, west on U.S. 30 to SR 61, and reverse for northbound motorists. Estimated completion: Friday, July 23, 2021

State Route 96 resurfacing - State Route 96, from just west of Technology Parkway to the SR 13/SR 96 junction, will have single lane closures for a smooth-seal resurfacing project. Traffic will be maintained by flaggers. Estimated completion: July 2021

State Route 309 resurfacing – State Route 309, from just north of SR 430 to N. Home Road, will have lane closures for a resurfacing project. Traffic will be maintained in 11’ lanes. Estimated completion: October 2021

State Route 603 consecutive culvert replacements

NEW IMPACTS

State Route 603, between Lucas Perrysville Road and Pleasant Valley Road, will close Monday, August 2 for three consecutive culvert replacements. The location of each culvert is as follows:

1) At the SR 603 and Lucas Perrysville Road intersection for approximately two weeks;

2) between Welty Road and Schrack Road for approximately one week; and

3) between Hunter Road and Pleasant Valley Road for approximately one week. The detour route for southbound motorists will be SR 603 to SR 39, east/southeast on SR 39 to SR 95, west on SR 95 to SR 603, and reverse for northbound motorists.

Estimated completion: Friday, Aug. 27, 2021.